é | ||||||
REUSE MASTER PLANNING PROCESS
Questions? Comments? Contact the Newport Chemical Depot Reuse Authority at:
259 Vine Street or send us an email at:
|
PROJECT WORK PLAN The following work plan identifies the three major planning phases and associated tasks to conduct and complete the Newport Chemical Depot Reuse Master Plan and Implementation Strategy. A detailed Project Schedule, which highlights key time periods for conducting specific tasks and illustrates relationships among tasks and phases of the study, is available at the bottom of the Schedule page.
PHASE A: PROJECT SCOPE REFINEMENT AND MANAGEMENT Task 1: Review / Refinement of Scope of Services and Schedule Task 2: Project Team / Client Update Meetings Task 3: Final Contract Terms and Conditions
PHASE B: INVENTORY AND ASSESSMENT ACTIVITIES Task 1: Community Involvement and Public Participation Sub-Task A: Stakeholder Interviews Sub-Task B: Focus Group Meetings Sub-Task C: General Public Meetings Sub-Task D: Teen / Youth Visioning Workshop Sub-Task E: Website Development and Management Task 2: Identification of Vermillion County and Regional Social Economic Conditions Task 3: Identification of NeCD Facilities Sub-Task A: Digital GIS Base Mapping Sub-Task B: Off-Base Context and Influences Analysis Sub-Task C: On-Base Conditions / Land, Buildings, and Facilities Sub-Task D: On-Base Conditions / Infrastructure Systems Sub-Task E: On-Base Conditions / Environmental Assessment Task 4: Market Potential of Land and Facilities Sub-Task A: Summary of Redevelopment Barriers Sub-Task B: Economic Development Targeting and Preliminary Task 5: Homeless Accommodation Considerations Task 6: Site-Wide Opportunities and Constraints Analysis and Development Suitability Map
PHASE C: CONCEPTUAL MASTER PLANNING Task 1: Planning and Development Framework Plan Workshop Task 2: Potential Use Site Requirements / Characteristics Analysis Task 3: Reuse Plan Alternatives Task 4: Disposition Strategies / Transfer Mechanisms Task 5: Alternative Plan Evaluation and Comparison Task 6: Alternative Plan Review Workshop Task 7: Preliminary “Preferred” NeCD Reuse Master Plan Task 8: Final NeCD Reuse Master Plan and Implementation Strategy Task 9: Potential Future Planning Studies (Optional)
For a complete description of the Project Work Plan and what is involved in each of the tasks outlined above, please view the Project Work Plan document below: Project Work Plan (187 kb - PDF) BASE REDEVELOPMENT PLANNING PROCESS The tasks shown above represent the project work plan specific to the redevelopment planning effort at the Newport Chemical Depot. For information regarding military base closure and base redevelopment planning in general, please review the following document, Base Redevelopment Planning for BRAC Sites, which presents an excellent overview of the base redevelopment planning process. This document was prepared by the Department of Defense Office of Economic Adjustment. More information about the BRAC planning process is also available from their website. Base Redevelopment Planning for BRAC Sites (1.07 mb - PDF) |
||||||